![]() |
Welcome to
Home Made Root Beer since 1994 |
Since 2010, the brewery has been open for social
activities to share the joy of drinking an assortment of
beverages. We had a rather large tent on the brewery patio
with some furniture for guests to sit and enjoy an
afternoon. More guests started coming as word spread about
us, causing us to get more furniture and pop-up tents to keep
the afternoon sun off of us. But after 2 years of
retirement from his day job, Mark decided that moving tents and
furniture to mow was too tiresome. It was time to have a
more permanent solution for entertainment.
And then, as if fortune shown down about them,
his fortune cookie said "Your willingness to take risks will
lead to opportunities that others fear."
So Mark & Laurel sat down and started to jot down some ideas. We started with an enclosed building so we could entertain more and hide from bad weather. Kind of costly. What about a smaller enclosed area with a large covered patio. Better. Eventually we settled on a smaller enclosed area mostly to store some stuff and a large covered patio, kind of like one of those park pavilions. We were very happy with the EPS solid core brewery building so we figured we would use the same manufactured structure. After calling around, we discovered ProCon in Faribault, Minnesota. After gagging over the cost, we decided to move forward. The plan was to be done by the end of October 2025, but a few snags got in the way of that schedule.
The final plans were a 24'x8'
enclosed building with an adjacent 24'x40' covered
pavilion. And it would go up near the existing
brewery. Electric but no plumbing. Sounded simple
enough. Just needed to get a permit from the county.
Ha! That took 3 months. For some reason they thought
we were running a business and wanted to treat the building as
such. Then they started looking at the existing brewery
building. Apparently they decided we needed a holding tank
for drainage water because the water was plumbed up to the
brewery from the house. And then they wanted us to inspect
the house septic tank and drain field. OMG!! All
this scrutiny for a building that did not even plan to have
water.
While we waited for the permit to be approved we
boldly contracted to have some trees
removed that would be in the way of the new
building. It was a shame to see so much shade be removed,
but the pavilion would provide its own shade. All in all 2
maple trees, an arborvitae, and a few branches of other trees
that were encroaching the area were removed. It really
opened up the area. Now we just need the permit to get
started on the construction.
Anyway, in mid-November (yep, just after
returning from WDW and 2 weeks after the original plan to be
finished) we got permit approved to build. Now, if you
know Minnesota, November is essentially part of winter.
Remember we got 30 inches of snow in the blizzard
on Halloween 1991. Pouring
concrete in the winter is kind of tricky but luckily this
year the weather stayed warm (above freezing) until 4 days after
the concrete was poured. Then it got cold and the snow
started to fall. The building
materials are now under 4-6 inches of snow and the
temperatures are staying below freezing. Not exactly ideal
for outside construction work.
After a couple week sabbatical the construction
crew arrived and the building construction
on the 8th of December. Admittedly, we were still fighting
cold (yep, below zero fahrenheit) and even more snow. But
the crew started putting up the structure. I was told that
they would work through the winter as long as the wind chill
remained above 0 F and it is not snowing/raining/sleeting (which
in Minnesota, that really leaves out a lot of days during a
normal winter). To their credit, on the 3rd day a few wall
panels and some of the support poles were up. Then they
finished the walls and added the roof trusses. About this
time, the thoughts were that they should be done with the
majority of the work by the first week of January. Some
work would need to to wait, specifically bring in about another 10 yards of fill to put
around the building and adding waiting until spring to
pour the cement apron in front of the doors. But this was
sounding very doable.
Then reality started to set in. More cold
weather and snow. After several years of nontraditional
winters in Minnesota had made us optimistic and forget what a
true Minnesota winter is like. I even heard a weather
person say it was going to be really cold and it the
temperatures were still going to be above 0oF.
We have become wimps! Needless to say, now that safety is
our number one concern of our society, progress on the building
project was rapidly slowing down. Humph!! Well, that
and half of every workday was spent clearing snow just to find
the build materials and work area. It is now new years day
and they are taking a holiday. Mind you, there have been
several days in the past two weeks that no one (or at most a
skeleton crew) have not shown up. And today it is not
snowing or insanely cold. I think I will take another
picture and then go up and make and amber beer - or bottle the
cider. At least I can make progress towards the
future. But first, maybe a nice breakfast of Eggs
Benedict.
=======================
More to come as progress continues.
=======================
The whole Glewwe family hopes you enjoy the
results of this project. Our products are still made by
hand in keeping with a traditional old world charm.
We will now have room for more entertaining. In fact, our 2nd Swiss slave is planning a wedding reception for the family & friends in the USA for September 2026. If you would like a tour of the brewery & pavilion, please feel free to contact us.
The final draft plans |
First we got to get the trees out of the way |
![]() There sure are a lot of pieces to this puzzle |
![]() Start with the
excavation, then pour the concrete floor, and inspection
|
The storage room and pavilion go up |
|
And we get power from the brewery |
And the inside is starting to take shape |
|
storage interior |
Pavilion exterior |
And we even have a sign welcoming our guests. |
Last modified December, 2025
Website Questions or Comments: Contact our webmistress
at glewwe-castle.com